Bringing 500 kV to the National Grid at Khartoum/Rabak | ICC Energy
Khartoum/Rabak Substation — ICC Energy DWC-LLC
ICC Energy — Project Feature
Bringing 500 kV to the National Grid at Khartoum/Rabak
A turnkey substation, built from cleared ground to full commissioning — how ICC Energy delivered Sudan's newest high-voltage transformation point for the Sudanese Electricity Transmission Company.
ICC Energy DWC-LLC | Khartoum/Rabak, Republic of Sudan
A New Anchor Point on Sudan's Transmission Backbone
On behalf of the Sudanese Electricity Transmission Company (SETCO), ICC Energy DWC-LLC designed, supplied, and constructed a 500/220 kV Power Transformation Substation and its associated interconnection works at Khartoum/Rabak. Delivered on a fully turnkey basis, the project represents ICC Energy's largest and highest-voltage substation to date — a facility built to step down Sudan's 500 kV transmission network to 220 kV distribution level, feeding one of the country's most critical grid corridors.
The contract called for a complete Design-Build-Turnkey delivery: engineering studies, equipment procurement, civil and electromechanical construction, testing, and final grid interconnection, all within a 24-month execution window.
More Than Megawatts
Reliable electricity is more than an engineering achievement — it is the foundation for economic growth, industrial development, healthcare, education, and improved quality of life. By strengthening one of Sudan's most important electricity corridors, the Khartoum/Rabak substation enhances the National Grid's ability to deliver reliable power to growing urban centres, industry, and essential public services, while improving network stability and long-term resilience for the country's future economic expansion.
Five Disciplines, One Integrated Handover
Constructed across a 120,000 m² site, the project required the coordination of engineering, procurement, civil works, testing, and grid interconnection into a single turnkey delivery:
"Successfully executed, received, and operated — and connected to the National Grid in accordance with the contract terms and to the satisfaction of the Employer."
— SETCO
Underneath that single line of certification sits everything the project represents: 24,000 meters of earthing conductor, ten 500 kV circuit breakers, two autotransformers each heavier than most substations' entire switchyards, and two years of engineering, procurement, and construction carried out to specification. For ICC Energy, Khartoum/Rabak stands as the company's most technically demanding transformation substation to date — and a marker of how far its EPC capability now reaches.